The company cited “unforeseen developments” that have made the project “unfeasible"
ALLO Communications is backing out of its 2025 contract with the City of Boulder to build last-mile fiber-optic infrastructure for the city. The company cited significant increases in labor and material costs, increased competition within the city, and AT&T’s acquisition of Lumen’s residential Quantum Fiber properties as the “unforeseen developments” that have made the project “unfeasible.”
The City of Boulder announced in November, 2024 that it chose ALLO as part of a “transformative agreement” to bring affordable, high speed internet access to the city. The city’s announcement also touted equity, inclusivity, and environmental sustainability as core tenets of the agreement by offering discounted rates to low-income community members. The service was initially announced to roll out in phases with the first installations expected to occur before the end of 2025.
“A buildout of a citywide fiber network has been a longstanding goal for our community, and it’s disappointing that we need to reset on this project,” City Manager Nuria Rivera-Vandermyde said. “We’ll be working to identify a new partner through a new procurement process, while also exploring our legal options in this unfortunate contract situation.”
The AT&T acquisition of Lumen’s Mass Market fiber business was a $5.75 billion transaction that included four million new locations across 11 states, including Denver and Boulder. ALLO sought voluntary resignations in June 2025 to cut costs as a result of delays to the federal Broadband Equity, Access, and Deployment (BEAD) program.
The City of Boulder retains all of ALLO’s $1.5 million rental payment and the company will continue to locate, maintain, and repair the City fiber ring at its own cost until the two parties can agree on a mutually-acceptable transition plan. ALLO said it hopes to find a resolution and hand-off duties to the city or a new contractor within 120 days.
ALLO Communications is backing out of its 2025 contract with the City of Boulder to build last-mile fiber-optic infrastructure for the city. The company cited significant increases in labor and material costs, increased competition within the city, and AT&T’s acquisition of Lumen’s residential Quantum Fiber properties as the “unforeseen developments” that have made the project “unfeasible.”
The City of Boulder announced in November, 2024 that it chose ALLO as part of a “transformative agreement” to bring affordable, high speed internet access to the city. The city’s announcement also touted equity, inclusivity, and environmental sustainability as core tenets of the agreement by offering discounted rates to low-income community members. The service was initially announced to roll out in phases with the first installations expected to occur before the end of 2025.
“A buildout of a citywide fiber network has been a longstanding goal for our community, and it’s disappointing that we need to reset on this project,” City Manager Nuria Rivera-Vandermyde said. “We’ll be working to identify a new partner through a new procurement process, while also exploring our legal options in this unfortunate contract situation.”
The AT&T acquisition of Lumen’s Mass Market fiber business was a $5.75 billion transaction that included four million new locations across 11 states, including Denver and Boulder. ALLO sought voluntary resignations in June 2025 to cut costs as a result of delays to the federal Broadband Equity, Access, and Deployment (BEAD) program.
The City of Boulder retains all of ALLO’s $1.5 million rental payment and the company will continue to locate, maintain, and repair the City fiber ring at its own cost until the two parties can agree on a mutually-acceptable transition plan. ALLO said it hopes to find a resolution and hand-off duties to the city or a new contractor within 120 days.