Fourmile Canyon paving work delayed, but July 3 still target date for completion

A problem with the subsurface requires extensive regrading and compaction or the asphalt on the surface will crumble under the weight of cars driving over it, according to Boulder County.

Fourmile Canyon paving work delayed, but July 3 still target date for completion

The Longmont Leader received the following update from Boulder County concerning Fourmile Canyon construction delays. The date references have been edited to reflect the time frames in conjuction with the day this item was posted:
*************************

As you may have seen, paving did not go as well as planned (last) week. The southern section, below Poorman, was completed, but the north section, above Logan Mill, did not get as far as they had liked. The delays are due to a problem with the subsurface, which has been found to be extremely soft in multiple sections of the downhill lane caused by water seeping up from below. This requires extensive regrading and compaction or the asphalt on the surface will crumble under the weight of cars driving over it. If you drive the canyon, you’ll see markings on the pavement that was laid where the asphalt is already cracking. Cracked asphalt will be removed and the road will be repaved. Lawrence has been working on the ground today and will will continue to work on the subsurface next week to get it suitable for paving. They’re working on rescheduling the paving subcontractor now. I’ll let you know when they plan on returning as soon as we know. As of (June 5), there will be no paving in the canyon (this) week. 

(This) week, in addition to grading and compaction of the north section, crews will be working on cutting ditches and finishing the gravel portion of the road shoulder throughout the canyon. A guardrail crew will also be on site starting Monday. This work will continue for the next two weeks. Expect travel delays between 8 a.m. and 5 p.m., Monday through Friday. 

We’re still shooting for a July 3 completion date, even with the paving problems we have encountered. 

*************************

Kylee Garson

About the Author: Kylee Garson

Read more

This has not been shared. Be the first!

Comments 0

Book your Trip to Longmont

Emotional Support Animals

Are you following the Colorado drought watering guidelines?

View Results

Loading ...